New solar energy projects from DBE Energy in Kırşehir and Şanlıurfa in 2026

Our group company DBE Energy reached important milestones in 2026 in its solar power plant projects in Kırşehir and Şanlıurfa. The plant in Kırşehir began generating energy in August, while energy acceptance procedures were completed for the project in Şanlıurfa.
The two projects bring DBE Energy's experience in engineering, procurement and construction (EPC) together with the goals of businesses that want to generate their own energy from the sun.
Kırşehir: Güncan Plastik SPP
The Güncan Plastik Solar Power Plant, built in the Mucur district of Kırşehir, has an installed capacity of 8 MW DC and 6 MW AC. The plant's acceptance procedures were completed on August 10, 2026, and the facility began generating energy.
The facility uses bifacial solar panel technology, which generates power from light reaching both the front and rear surfaces of the panel. The plant is connected to the grid via 18 inverters and is monitored by DBE Energy's central monitoring system.
Why do bifacial panels matter?
While conventional panels generate energy only from sunlight falling on their front surface, bifacial panels can also use light reflected from the ground and surroundings on their rear surface. This allows higher energy yield from the same area.
How efficiently this technology performs depends on the height of the panels above the ground, the spacing between rows and the mounting structure design. That is why project engineering is one of the decisive factors in plant performance.
Şanlıurfa: Bucaklar Yağ SPP
The Bucaklar Yağ Solar Power Plant in the Siverek district of Şanlıurfa has an installed capacity of 4.5 MW DC and 3.45 MW AC. Energy acceptance procedures for the project have been completed, and applications for the SPP acceptance have also been filed.
The high solar irradiation potential of Southeastern Anatolia makes plants in the region stand out for efficient generation. The project sets an example for industrial companies in the region transitioning to renewable energy.
From project to acceptance
A solar power plant goes through project development and engineering, equipment procurement, site installation, commissioning and acceptance before it starts generating. With energy acceptance, the plant becomes able to feed energy into the grid, and with SPP acceptance, the facility's acceptance process is completed.
DBE Energy can manage all of these stages from a single source. This approach ensures that projects are completed on schedule and that investors work with a single point of contact.
From installation to operation, from a single source
Once the plants it builds are commissioned, DBE Energy can also provide operation and maintenance services. The company's operation and maintenance portfolio, which stood at around 100 MW in 2025, continues to grow in 2026 as new plants are added.
Services such as scheduled maintenance programs, panel inspections with thermal imaging, DC insulation tests and I-V curve measurements aim to keep plants running at high performance for many years. The plants are monitored 24/7 by the central monitoring team.
Supporting sustainable generation
As DBE Holding, we continue to support businesses' transition to sustainable energy generation through the engineering and implementation experience of our subsidiary DBE Energy in renewable energy.
Founded in İstanbul in 2013, DBE Energy operates in EPC, operation and maintenance, and project development. In addition to solar energy, the company also provides services in EV charging stations, energy storage systems and aggregation in the electricity market.